This project and utility are fictional. Harborview Solar and Harbor Valley Electric Cooperative do not exist. The findings below were written to show the report format.
- Project
- Harborview Solar, 2.4 MW AC
- Utility
- Harbor Valley Electric Cooperative
- Findings
- 7 (2 High, 3 Medium, 2 Low)
- HighOne-line diagram has no PE stamp
The manual requires a one-line diagram stamped by a licensed professional engineer. Drawing E-101 has no stamp or seal.
Citation: Interconnection Manual, section 4.2(b), page 18
- HighNo site control for the gen-tie easement
The packet shows site control for the array parcel but not for the easement the gen-tie line crosses.
Citation: Interconnection Manual, section 3.1, page 9
- MediumInverter capacity differs: 2,400 kW on the application, 2,500 kW on the one-line
The two documents give different totals. Correct the one that is wrong so the packet shows a single capacity.
Citation: Application Form, Part B; Drawing E-101
- MediumSite plan does not mark the point of interconnection
Drawing C-201 shows the array and access road but not where the project connects to the feeder.
Citation: Interconnection Manual, section 4.3(a), page 20
- MediumRelay settings are missing
The packet lists the protective relay models but not the proposed settings the manual asks for.
Citation: Interconnection Manual, section 5.4, page 27
- LowProject name differs between documents
The application says "Harborview Solar". The title block on Drawing C-201 says "Harbor View Solar".
Citation: Application Form, Part A; Drawing C-201
- LowOne-line diagram has no revision date
The title block on Drawing E-101 leaves the revision date blank.
Citation: Interconnection Manual, section 4.2(d), page 19
Findings are advisory and always subject to human review.